Atuabo Gas Processing Plant
Ghana Grid Company is urging Ghanaians to remain calm as measures have been put in place to avert the impact of the shut down of Atuabo Gas Processing Plant.
According to CEO of GRIDCo Jonathan Amoako-Baah, plans have been made to use other sources of fuel to run the plants in place of gas.
The valve of Atuabo Gas Processing plant in the Western Region was closed at 09.25hrs today, Saturday, March 30, 2019, for a 12-day outage to complete the final tie-in works under the Takoradi-Tema Interconnection Project.