The Transmission Company of Nigeria (TCN) has restored full bulk power to its 132/33kV Apo Transmission Substation, effective Thursday, January 23, 2025.

This restoration followed the successful relocation of eight 132kV and 33kV towers along the Kukwaba/Apo 132kV line (Southern Expressway route), necessitated by the Federal Capital Development Agency’s (FCDA) road dualization project along the Apo axis.

According to TCN, the two-week relocation work, which commenced on Monday, January 6, 2025, involved dismantling and reconstructing the towers, as well as restringing power cables.

“With the restoration of full bulk power, Abuja DisCo can now provide normal electricity supply from the substation to its customers in the affected areas, ending the previous load rationing,” TCN said.

TCN expressed appreciation to Nigerians for their patience and understanding during this period.

 

 

 

 