Ghana: Claims By INSTEPR GNPC Has Postponed Decommissioning Of Saltpond Oil Rig False

0
309

Ghana’s national oil company, GNPC, has described misleading claims by the Institute for Energy Policies Research (INSTEPR) that the West African nation risks paying judgment debt over stalled decommissioning of Saltpond Offshore Oil Rig in the Central Region.

According to the GNPC,  its acting CEO has not indefinitely postponed a meeting with the contractor for the commencement of the second phase of the decommissioning exercise, saying INSTEPR’s claim is false.

“It is, therefore, not correct for INSTEPR to suggest that the new Chief Executive (Mr Opoku Danquah) has postponed and subsequently cancelled the ‘meeting to start phase 2 indefinitely’.  On June 27, 2022, the Chief Executive Officer of GNPC had written to the Contractor (Hans & Co) confirming July 14, 2022, as the date for the Kick-Off meeting after consultations with the Contractor and Petroleum Commission,” a statement from the GNPC said.

In a statement issued on 27th June 2022, Executive Director, Kwadwo Opoku, said: “INSTEPR has seen a letter written by HANS & Co. to Petroleum Commission on the 15th June 2022, complaining about the delay to start phase 2 of the project. This delay is costing the project since all logistics to move the Rig (Trident VIII) from Nigeria to Ghana have already been contracted and paid. The company has committed to service boats, paid for fuel in storage and hired personnel for the work.

“Anyone familiar with the upstream drilling industry will know that Jack-up Rigs are only available during certain windows, and it might take years to get another Rig available if Hans & Co. does not use the Rig Trident VIII within the specified period in this contract.

“Why are the new acting Managing Director and the board of directors acting to frustrate the decommissioning of the Saltpond field? Our investigation has not yielded any concrete reasons yet. There is one thing for certain, the cost of the project could quadruple if the posture of the Chief Executive Officer continues and possible multi-million-dollar judgement debt for breach of contract,” INSTEPR said in its statement.

Reacting to the claims by INSTEPR, GNPC explained that following the inspection of the equipment to be utilised in the decommissioning exercise in Nigeria, no definite date for the ‘kick-off’ meeting was set.

Ghana: GNPC Workers Wanted To Kill Me For Sending Over 800 People Home-Former CEO

The statement pointed out that dates were proposed, pending the team meeting all the statutory approvals.

“GNPC has been working with the Contractor to meet certain regulatory requirements necessary to prove the Contractor’s capacity and readiness to execute the decommissioning of the field,” it added.

Below is the full statement:

Re: Impending Judgment Debt at GNPC Over Stalled Saltpond Field Decommission Project

The Ghana National Petroleum Corporation (GNPC) has taken note of a Press Release dated June 27, 2022 from the Institute for Energy Policies and Research (INSTEPR), signed by its Executive Director, on the above subject.  Subsequent to this, the Business and Financial Times (B&FT) newspaper also carried a frontpage story in the June 28, 2022 edition with a heading “Judgment debt, oil spillage loom over stalled Saltpond rig decommission” referencing the said press release.

GNPC will like to set the record straight on some of the inaccuracies contained in the press release from INSTEPR and the B&FT publication as follows:

Following the inspection of the equipment to be utilized in the decommissioning exercise in Nigeria, no definite date for the ‘kick-off’ meeting was set. However, dates were proposed pending the team meeting all the statutory approvals. GNPC has been working with the Contractor to meet certain regulatory requirements necessary to prove the Contractor’s capacity and readiness to execute the decommissioning of the field. It is therefore not correct for INSTEPR or B&FT to suggest that the new Chief Executive (Mr. Opoku Danquah) has postponed and subsequently cancelled the ‘meeting to start phase 2 indefinitely’.  On June 27, 2022, the Chief Executive Officer of GNPC had written to the Contractor (Hans & Co) confirming July 14, 2022, as the date for the Kick-Off meeting after consultations with the Contractor and Petroleum Commission.

Whilst it is an indisputable fact that Mr. Opoku Danquah before his appointment was the DCE Technical Operations and may have been aware of the fallouts from the negotiation process, he was at no time part of, or present at, the meetings of the negotiation team.

The negotiation team was made of staff from the Technical, Procurement, Finance and Legal Departments of the Corporation, and they reported to the Chief Executive Officer. 

The fact remains that GNPC continues to engage the Contractor at every stage of the project and updates Petroleum Commission, the upstream regulator. We have come a long way working with the same Contractor to satisfy all regulatory and permitting requirements which would pave the way for the commencement of the project.

GNPC has done extensive community engagement with all stakeholders and supported the Chiefs and people of the project affected communities to perform all the traditional rights required to commence the decommissioning.

The Chief Executive Officer and the Board cannot, therefore, be said to be ‘acting to frustrate the decommissioning of the Saltpond Field’.

GNPC assures INSTEPR and the public that it remains committed to the start and successful completion of the Decommissioning Project.

We will therefore expect INSTEPR to correct the wrong impression created, and for B&FT to retract the said unfortunate publication.

 

 

 

 

Source: https://energynewsafrica.com

 

 

 

 

 

 

 

 

 

 

 

 

 


Discover more from Energy News Africa

Subscribe to get the latest posts sent to your email.