Ghana’s Take-or-pay Obligation To Reduce Significantly-GNPC CEO

0
1223

The Chief Executive Officer of Ghana’s National Oil Company (GNPC), Dr K.K. Sarpong, is optimistic that, with the corporation’s drive to increase the utilisation of domestic gas, the take-or-pay obligation of the country will be reduced significantly.

His hopes follow the successful completion of the initial phase-Takoradi scope-of the Takoradi-Tema Interconnection Project, which will allow reverse flow of gas from the Western Region of Ghana to the Tema power enclave.

“The successful execution of this scope of the project paves the way for the smooth flow of gas from the Western Region to Tema for use by the various gas off-takers in the Tema-Accra power and industrial enclave.

“This project has also doubled the capacity of Ghana Gas to transport GNPC’s gas to feed critical national power generation facilities sited in the Western enclave. Again, gas users in the Accra-Tema region are assured of relatively more reliable gas supply through the TTIP,” a statement copied to the energynewsafrica.com said.

According to the CEO of GNPC, “Ghana Gas’ ability to supply gas for a stable production of electricity means that, cost of electricity to the final consumer will now be relatively lower as compared to the use of Heavy Fuel Oil (HFO) or diesel as fuel for electricity generation.”

He further stated that the cost of production for local companies especially in the manufacturing and mining sectors, would reduce significantly to enable them become more competitive

This feat was achieved with the support and collaboration of ENI Ghana Exploration and Production Ltd., Vitol Ghana Upstream, Ghana National Gas Company (Ghana Gas) and the West Africa Gas Pipeline Company (WAPCo).

Commissioning and performance testing of the Takoradi scope of the ‘Takoradi–Tema Interconnection Project’ (TTIP) has been successfully carried out.

The Tema section of the TTIP, which includes the revamping of WAPCo Tema Regulatory and Metering Station (RMS), is ongoing and is expected to be completed by the fourth quarter of 2019.

“As the National Gas Aggregator, GNPC played an enabler role, providing the financing and necessary comforts to the partners to ensure the successful completion of the project. GNPC engineers also provided end-to-end advice in the design and scoping, as well as monitoring of the project execution,” the statement concluded.

 

Source: www.energynewsafrica.com