Chinese oil and gas giant, CNOOC has commenced production at Bozhong 19-2 Oilfield Development Project with an estimated peak production of approximately 18,000 barrels of heavy crude oil per day.

Situated in central Bohai Bay, with an average water depth of approximately 20 meters, the project comprises a new central processing platform and four new unmanned wellhead platforms.

The development plan includes the commissioning of a total of 59 wells, consisting of 34 production wells and 25 water-injection wells.

The implementation of smart engineering and standardized construction has reduced the project’s construction cycle. CNOOC holds 100% operating interest in the project.

It has strongly promoted the efficient development of offshore oil and gas resources and laid a solid foundation for the production growth in the Bohai oilfields, the largest crude oil production base in China, CNOOC said in a press release.

 

 