Ghana: TOR MD Was Forced To Resign For Refusing To Approve  ‘Stinking’ Deal-IES

0
2440
Mr. Isaac Osei, Outgoing Managing Director of TOR, Republic of Ghana

The Institute of Energy Security (IES), an energy think tank in the Republic of Ghana is alleging that the Managing Director for Tema Oil Refinery (TOR), Isaac Osei, was compelled to resign following his refusal to approve a shady deal.

Energynewsafrica.com last Friday reported the resignation of the Managing Director of TOR, Mr Isaac Osei.

It was not clear why he decided to resign.

However, IES in a press release copied to energynewsafrica.com, stated that its investigations revealed Mr. Osei left his position after he refused to sign off on a deal to refine 11 million barrels of crude oil at a cost of US$1.5 instead of a market rate of US$4.5 per barrel.

According to the statement, should TOR agree to the terms that were being imposed on it, the refinery would not be able to recover its operational costs much less talk of making any gain on the transaction.

“It is this unfair and uneconomical agreement that some persons of interest were exerting pressure on Mr. Osei to sign-off, or resign instead. Had he agreed to this, the huge difference in the questionably discounted Tolling Agreement running into millions of dollars would have gone into private pockets as effortless profit.

To the public purse, however, this will be hard debts to be borne by the Ghanaian taxpayer without anyone being prosecuted for it. It would have simply been explained as usual as bad debts due to “management mistakes and wrong judgment,” the statement said.

Below is the full statement issued by IES

ANOTHER QUESTIONABLE SCHEME TO HURT THIS COUNTRY IN THE OFFING

  1. The Institute for Energy Security (IES) wishes to first and foremost commend the outgoing Managing Director (MD) of the Tema Oil Refinery (TOR) for choosing a path of integrity (resignation) rather than to continue as MD and invariably become a party to a questionable scheme that would hurt this country, benefit few private individuals, and saddle TOR and Ghana with more debts.
  2. Investigations by the IES indicates that the MD of TOR was forced to leave his post for refusing to sign-off a Tolling Agreement (TA) at a rate of US$1.5 per barrel for the utilization of both the Crude Distillation Unit (CDU) and the Residual Fluid Catalytic Cracker (RFCC); instead of an average rate of US$4.5 per barrel for an $11m barrel cargo to be refined.
  3. Currently, TOR charges Vitol/WoodfieldsUS$2.5 per barrel for the utilization of only the CDU, without the use of the RFCC. Should TOR agree to sign for a Tolling Fee of US$1.5 per barrel, the entity would be unable to cover operational cost, let alone start and operate the plant; as TOR needs a minimum revenue of $US6 million on monthly basis to begin to recover, assuming no debt is paid.
  4. It is this unfair and uneconomical agreement that some persons of interest were exerting pressure on Mr. Osei to sign-off, or resign instead. Had he agreed to this, the huge difference in the questionably discounted Tolling Agreement running into millions of dollars would have gone into private pockets as effortless profit.

To the public purse, however, this will be hard debts to be borne by the Ghanaian taxpayer without anyone being prosecuted for it. It would have simply been explained as usual as bad debts due to “management mistakes and wrong judgment.”

  1. It would be recalled that IES in January 2018 called on the government to arrest the leadership crisis at TOR which subsequently led to a loss of over $24 million in just one transaction and bad judgment. Almost three years under his leadership the refinery still struggles to operate at full capacity, with low asset utilization.
  2. While the IES has had issues with Isaac Osei’s leadership of TOR in the past and would have expected to see him sacked months ago, his recent resignation and the issues outlined above present him as a bold spirit in the fight against corruption, stealing, and patronage.
  3. The Institute would do Ghana a great disservice if the issues surrounding Mr. Osei’s resignation are not publicly and clearly laid bare for the Ghanaian public to understand, and to be prepared to bear a potential loss of US$27.5 million to the state, if TOR subsequently agrees to process the 11 million barrels of crude on account of some greedy institution and personalities.
  4. While the IES is fully aware that the government is taking drastic steps to appoint a “more cooperative” MD to take-over

 

 

 

Source: www.energynewsafrica.com

 