Ghana National Gas Company has resolved the technical fault that occured at its Atuabo Gas Processing Plant, which resulted in limited gas supply for power generation plants.
In a statement issued by Ernest Kofi Owusu- Bempah Bonsu, Corporate Communications Manager, he said there was a plant equipment trip on Wednesday, September 25, 2024, which resulted in limited gas flow rate from the plant to power generators.
He explained that immediately, the company’s engineers started working and successfully resolved the issue and restarted the plant.
“We are currently flowing at 40MMscfd which is about 45% of our normal flow,” he said.
He added: “Our team is working assiduously around the clock to ensure power stability of the plant.”
He apologised to Ghanaians for the inconvenience caused and assured that there would be full gas flow for power generation in due course.